The conceptual proposal of this Hi-Tech Park was approved by State Town and Rural Planning Department of Pahang (JPBD) on 19th August 2009. In its approval, it is stated that National Physical Planning Council (MPFN) of 10/2009 dated on July 23, 2009, which was chaired by the present Prime Minister of Malaysia, had endorsed this proposal under the Private Funding Initiative (PFI) model.

Kuantan Hi-Tech Park (KuHTP) is based on 3 parcels of land. Pharmaceutical high tech industry shall be the key driven player besides of others multicipline high tech industry.

It involve of Master infrastucture planning and performance standard establishment of Utilities requirement for the new High Tech Park. The total electrical consumption is estimated about 185 MVA which shall be supplied by new PMU. A maximum no of power fault notification shall limited to less than 1 hour and the time of restoration shall be within 4 hours under Utilities peformance standard.